COLOMBO, Sri Lanka – 30 October 2026 – Sri Lanka’s construction sector maintained its growth trajectory in September 2026, as revealed by the latest Purchasing Managers’ Index (PMI) for Construction. The Central Bank of Sri Lanka (CBSL) announced today that the Total Activity Index for Construction recorded 57.8, signalling continued expansion, albeit at a slightly slower pace than the previous month.
According to the CBSL Statistics Department, the sustained growth was primarily propelled by a consistent influx of new construction projects. This positive momentum reflects ongoing development activities within the nation, with a notable contribution from government-funded initiatives.
Key Indicators Point to Growth, Yet Challenges Persist
A deeper dive into the sub-indices of the PMI – Construction report for September 2026 reveals a mixed picture of robust activity alongside lingering constraints:
- New Orders Index: This index expanded at a higher pace, registering 65.6 (up from 62.5 in August). This acceleration was largely attributed to an increase in government-funded projects, underscoring the state’s continued investment in infrastructure and development.
- Employment Index: Reflecting the increase in project availability, the Employment Index grew at a moderate rate, reaching 58.1. Firms reported ongoing recruitments, although the persistent shortage of skilled workers remained a significant impediment.
- Quantity of Purchases Index: This index saw a higher rate of increase, climbing to 62.5 (from 59.4 in August). This reflects the growing procurement requirements stemming from both ongoing and newly awarded projects.
- Suppliers’ Delivery Times Index: A concerning trend, this index lengthened further to 65.6 (from 59.4 in August). This indicates sustained supply-side pressures, impacting the timely completion of projects.
Bitumen Shortage Hampers Road Projects, Skilled Labour a Constant Concern
Despite the overall expansion, the report highlighted critical bottlenecks affecting the sector’s efficiency. The shortage of bitumen was identified as a major constraint, directly leading to delays in several vital road construction projects across the country. This issue underscores supply chain vulnerabilities and their direct impact on key infrastructure development.
Furthermore, the long-standing problem of skilled labour shortages continues to plague the industry. While recruitment efforts are underway, many construction firms report difficulties in filling positions that require specialised expertise, potentially affecting project quality and timelines.
Positive Outlook for Q4 2026 Despite Headwinds
Looking ahead, expectations for construction activity over the next three months remain positive. This optimistic outlook is largely underpinned by the pipeline of newly awarded projects, which are anticipated to drive demand and activity. However, the report cautions that ongoing challenges related to the availability of key materials and skilled labour are expected to persist, requiring strategic interventions.
In a global context, while Sri Lanka’s construction sector continues to expand, several major economies like the Eurozone, France, Germany, and the UK reported falling or slower rates of contraction in their respective PMI figures for September 2026, according to S&P Global data. Ireland, however, also saw a rising, slower rate of growth.
The CBSL compiles the PMI – Construction index using a diffusion index methodology, where a reading above 50 indicates expansion. The survey targets high-graded local construction companies registered with the Construction Industry Development Authority.
Source: Read original document