LankaBIZ Industry Intelligence

Sri Lanka Construction Industry Tracker

Construction activity • GDP contribution • PMI • Building materials • Cement supply • Construction costs • Credit and financing • Infrastructure pipeline • Housing • Labour • Contractors • Risks and investment opportunities
Research cut-off: 14 November 2026 Latest PMI: August 2026 Latest cement: August 2026 Latest building-material imports: September 2026 CBSL • DCS • CIDA • Treasury
59.4
Latest Construction PMI / 100
EXPANSIONARY, WITH INPUT-SIDE CONSTRAINTS — Construction activity expanded in August 2026, with the PMI Total Activity Index at 59.4. New orders continued to increase, supported mainly by government-funded projects. Employment and purchases remained in expansion territory, but bitumen shortages, skilled-labour constraints and volatile material prices limited the pace of execution. The sector’s 2025 real growth of 9.2% and first-half 2026 growth of 15.1% point to a recovery that is continuing, although project delivery and cost control remain critical.
PMI interpretation: above 50 = expansion; below 50 = contraction. PMI is a diffusion index, not a percentage growth rate.
2025 Real Sector Growth
+9.2%
Construction GDP
H1 2026 Real Growth
+15.1%
Year-on-year
August 2026 PMI
59.4
Expansion
Construction Credit
Rs.1.96tn
August 2026 outstanding
2026 Road Allocation
Rs.342bn
Government budget

Construction Industry Activity Index

Central Bank Construction PMI Total Activity Index, January–August 2026. The neutral threshold is 50. Monthly readings are actual survey results, not estimates.
January 2026
75.0
April 2026
45.7
August 2026
59.4

Interpretation: the index fell below the 50-point threshold in April, indicating contraction, before returning to expansion in May. August remained expansionary but eased from July’s 61.4. The CBSL identified bitumen shortages as a continuing constraint on road construction progress.

Construction GDP & Economic Contribution

Real growth at constant 2015 prices; 2025 and first-half 2026 provisional national accounts.
PeriodConstruction growthGDP growthReading
2022-20.9%-7.3%Deep contraction
2023-20.8%-2.3%Continued contraction
2024+19.4%+5.0%Recovery
2025+9.2%+5.0%Expansion
H1 2025+9.6%+4.8%Expansion
H1 2026+15.1%+4.7%Faster growth
The DCS national accounts table reports 2024 construction growth at 19.4%; some earlier releases and industry commentary have cited 20.1% following revisions. Use the latest national accounts series for consistent comparisons.

Annual Construction Growth

Real year-on-year growth, selected years.
2023 trough
-20.8%
2025 growth
+9.2%
H1 2026
+15.1%

Construction PMI Monitor

Monthly total activity index and movement around the neutral 50 threshold.
Month 2026PMIDirection
January75.0Expansion
February70.3Expansion
March57.1Expansion
April45.7Contraction
May59.1Expansion
June60.0Expansion
July61.4Expansion
August59.4Expansion

What is driving activity?

New orders
New orders increased further in August, mainly driven by government-funded projects.
Employment and purchases
Both indices remained in expansion territory in August.
Suppliers’ delivery times
Delivery times remained extended, reflecting workloads and supply-chain pressures.
Bitumen and skilled labour
Bitumen shortages, skilled-worker gaps and raw-material constraints continued to limit progress.

Construction Materials Monitor — Cement

CBSL monthly construction statistics. Latest available observations: August 2026. Volumes in thousand metric tonnes.
Local production · Aug
440,000 MT
Imports · Aug
52,000 MT
Total supply · Aug
492,000 MT
Month 2026Local production (‘000 MT)Imports (‘000 MT)Total supply (‘000 MT)
January41441455
February38752439
March49587582
April31952371
May39258449
June35751408
July40154455
August44052492
Total supply is local production plus imports; it is not equivalent to cement consumption because inventory changes, exports and distribution timing may differ.

Construction Cost Index

CIDA All Construction Cost Index, base 1990 = 100. Latest available: Q4 2025.
Q4 2025 index
1,377.2
Quarterly change
+0.8%
Base year
1990=100
This official index ends at Q4 2025. It should not be extrapolated as a current 2026 construction-cost quote. Industry commentary in August 2026 described renewed cost pressures, but its estimate of 20–30% above 2025 benchmarks is an industry assessment, not an official index observation.

Building Materials Import Monitor

Imports of building materials, US$ million, latest CBSL observation September 2026.
September 2026
US$123.94m
Month-on-month
+61.6%
August 2026
US$76.70m
The series includes building materials as classified in CBSL merchandise trade statistics. It is a broad import-value measure and should not be interpreted as a pure construction-volume indicator.

Construction Sector Credit

Outstanding commercial-bank credit to the construction sector, Rs. billion.
August 2026
Rs.1,959bn
July 2026
Rs.1,940bn
MoM change
+1.0%
CBSL sectoral private-sector credit series from April 2025. Credit outstanding reflects bank lending exposure, not the value of new construction contracts or actual sector output.

Housing & Private-Sector Demand

Residential activity
Industry commentary in September 2026 indicated improving residential construction and retail-driven cement demand.
Heavy construction
The Chamber of Construction Industry reported that heavy construction remained slower, with weak state spending and marginal steel-consumption growth.
Housing approvals
Greater Colombo Housing Approvals Index is a useful leading indicator; the dashboard should ingest each new quarterly DCS/CBSL observation before updating this series.
Commercial and tourism projects
Improving business confidence and hotel, commercial and industrial investment can support private-sector demand, subject to financing and project execution.

Government Infrastructure & Project Pipeline

Selected 2026 Budget allocations. These are budget allocations, not proof of disbursement, contract award or completed construction.
Overall road development
Rs.342bn
Kadawatha–Mirigama
Rs.66.15bn
Central Expressway Phase III
Rs.10.5bn
Project / programme2026 allocationIndustry relevance
Overall road developmentRs.342.0bnRoads, bridges, aggregates, bitumen, machinery
Kadawatha–Mirigama Central ExpresswayRs.66.15bnMajor civil works and construction materials
Central Expressway Phase III / Pothuhera–Rambukkana–GalagedaraRs.10.5bnExpressway construction and completion works
Rambukkana–Galagedara section proposalRs.20.0bnProposed domestic-funded construction
Urban regeneration housingRs.15.0bnHousing construction and urban infrastructure
Rural roadsRs.24.0bnRegional connectivity and local contractors
Rural bridgesRs.2.5bnBridge construction and engineering
The allocations above are selected items from the 2026 Budget and should not be added together as a complete, non-overlapping construction-sector expenditure total. Some project allocations may be included within the overall road-development allocation.

Industry Structure & Value Chain

Core business segments monitored by LankaBIZ.
Infrastructure & civil engineeringRoads, expressways, bridges, ports, airports, water supply, drainage and irrigation.
Residential constructionHousing, apartments, condominiums, renovations and urban regeneration.
Commercial & industrialHotels, offices, factories, warehouses, logistics facilities and industrial parks.
Construction materialsCement, ready-mix concrete, steel, aggregates, sand, bitumen, tiles, glass and finishing products.
Professional servicesArchitecture, quantity surveying, engineering design, project management and supervision.
Equipment & contractingHeavy machinery, plant hire, earthworks, specialist subcontracting and maintenance.

Industry Risk Monitor

Input shortages and price volatility
Bitumen availability, imported steel and other materials, fuel and transport costs can disrupt schedules and compress margins.
Skilled labour shortages
Shortages of experienced tradespeople and engineers affect productivity, delivery times and wage costs.
Public-project execution
Budget allocations translate into industry demand only when funding, procurement, land acquisition and implementation progress.
Working capital and payment delays
Contractors face cash-flow exposure when certification, client payments and material purchases are mismatched.
Fixed-price contract exposure
Cost escalation between tender and procurement can erode margins where price-adjustment clauses are absent or inadequate.

LankaBIZ AI Construction Outlook

Near term: leading indicators point to expansion. PMI was 59.4 in August, cement supply was 492,000 MT in August and building-material imports rose to US$123.94m in September. However, these measures have different coverage and should not be treated as interchangeable measures of output.

Demand: the 2026 road-development budget and continued new orders provide a public-sector pipeline. Residential construction is showing signs of improvement, while heavy construction remains more dependent on state project execution.

Costs and margins: the official CIDA cost index is available only through Q4 2025 in the cited series. Industry commentary in August 2026 described renewed material and labour cost pressures. Contractors should refresh project estimates, contingency provisions and price-adjustment clauses.

Medium term: sustainable growth requires predictable public procurement, stronger private investment, improved access to project finance, reliable material supply and a larger skilled workforce.

Strategic opportunity: digital project controls, BIM, prefabrication, energy-efficient buildings, local material substitution and modern procurement can improve productivity and reduce project risk.

LankaBIZ Construction Data Engine

Recommended data layer for monthly monitoring, automated collection, historical storage and editorial approval.
DatasetFrequencyPrimary sourcePriority
Construction PMI: activity, orders, employment, purchasesMonthlyCBSL / S&P GlobalHigh
Construction GDP / value addedQuarterly / AnnualDCS / CBSLHigh
Cement local production, imports and supplyMonthlyCBSL / Customs / industryHigh
Construction cost indices by building typeQuarterlyCIDA / CBSLHigh
Building material importsMonthlyCBSL / CustomsHigh
Steel, bitumen, sand and aggregate pricesMonthlyCIDA / suppliers / market surveyHigh
Construction sector creditMonthlyCBSLHigh
Housing approvals and building permitsQuarterlyDCS / local authoritiesMedium
Public infrastructure project progressMonthly / QuarterlyTreasury / line ministries / RDAHigh
Contract awards and procurement noticesEvent-basedGovernment procurement portals / CIDAHigh
Employment, wages and skillsQuarterly / AnnualDCS / Labour Department / CCIMedium
Listed construction and material companiesQuarterlyCSE filings / company reportsHigh

Primary Sources & Methodology

Official and industry sources used for this research cut-off. Series periods and definitions differ and are labelled in the dashboard.